Main Street Reconstruction Update: Starting work on water main and Town Common

The Town issued another update on the Main Street Reconstruction Project. Here’s the latest on work taking place this week:

The Main Street Project will continue to work on the water by-pass during the week of 5/5.

Water main replacement will begin during the week of 5-5 and will continue for a couple of months.
This work will include trenching in the street.
This work will cause traffic delays.
This work will start in the area of Sears Road and progress east.

Work on the Town Common Stone Wall Has Started
The immediate work includes removing and storing the capstones and digging and pouring a foundation for the wall.
This work will be ongoing for several weeks.